AnsweredAssumed Answered

MSP not refresh schedule data

Question asked by kduchacek on Jan 25, 2016
Latest reply on Feb 17, 2016 by kduchacek

Hi,

Does anybody have the same experience with Clarity (Gantt) -> MSP scheduling?

The configuration:  Clarity 14.3, MSP-2010, Scheduler connector form Clarity14.3

  1. When I create tasks in MSP and save it in Clarity it works fine.
  2. After that I reschedule any task through Clarity Gantt (move it). The start and finish date are changed in Clarity.
  3. After that I open the project in MSP again and the start and finish dates are not promoted.

Is there any general setting in MSP or Clarity?

 

clarity1.jpg

Clarity2.jpg

 

msp.JPG

 

Thanks Karel

Outcomes