Task is marked as Complete and can't change the status

Question asked by MindyA on Jan 28, 2016
Latest reply on Jan 29, 2016 by Connie_Fu

This is for Clarity 14.3

 

We have a task that is marked as Completed 100%.  We are trying to change the status to Not Started/Started but are unable to.

 

there are ETCs on resources and roles on this task. 

Someone charged time against this task in July 2015 and then removed the time in a timesheet.

 

Any suggestions on what to do?