Hi,

 

I am seeing a situation in clarity where for some resources(very few) having allocation finish date less than start date.  In what instances this happens. I would expect system should not allow this to happen. Any thoughts?

 

Allocation start date: 10/22/12

Allocation finish date: 10/21/12

 

While in DB I see start and finish dates as 2012-10-22 00:00:00.0.

 

Also I also see a situation like Finish date in DB is 1 day greater than start(but not for every one) when will this happen and what is the logic behind these scenarios. Any help appreciated