    Hi,

    I am trying to update Project Finish Date of the parent project which has a sub-project. Both parent and child don't have tasks and both don't have team set up, there is no alloications/estimates/assignements.

    However, I cannot modify the project finish date of the parent even if move the sub-project finish date. I can only do this when I unlink the sub-project and then re-link it again.

    Is it how it is supposed to work out-of-the box?

    Thank you all for the help.



  • 2.  Re: Project Finish Date in CA PPM 14.3

    Posted Mar 22, 2016 04:10 PM

    You are using CA PPM 14.3, any patches? I tried to duplicate in my environment and could not.



  • 3.  Re: Project Finish Date in CA PPM 14.3

    Posted Mar 22, 2016 04:29 PM

    yes. we are using 14.3 and I think the latest patch