Baseline not matching Budget

Question asked by Tonya.A on Mar 17, 2016
Latest reply on Mar 18, 2016 by Kathryn_Ellis

I am new to Clarity (just started using it about 6 weeks ago) and am trying to figure out how the baseline and budgets work.  I created a cost plan and auto-populated it based on task assignments.  It is the plan of record and also submitted it as the approved budget.  Then - I created a baseline.  Why are the two total cost amounts different?  Shouldn't the baseline and the budget be the exact same Total Cost?  The budgeted cost is $125k but the BAC is calculating at $89k.  Any help with this?