  • 1.  Field Schedule Variance %

    Posted Apr 04, 2016 03:07 PM

    Hello everybody, I contact with this comunity because I need to know which is the calculate that does the field  Schedule Variance % that appear in the task object.

     

    When I add this field in the list of tasks appear empty.

    ListOfTaskt.jpg

     

    In this field appear the following calculat:

    ((ev_bcwp - ev_bcws)/ ev_bcws)*100

     

    Note: At this moment we do not assign resources to tasks.

     

    Regards.

    Patricio.



  • 2.  Re: Field Schedule Variance %

    Posted Apr 04, 2016 04:19 PM

    Hi Patricio. Schedule Variance is an Earned Value Management measure. Without financially enabled resources assigned to tasks and CA PPM's Earned Value Management capability running - any field like this that relies on the Earned Value calculations will appear blank.