Question asked by Patricio_1979 on Apr 4, 2016

Hello everybody, I contact with this comunity because I need to know which is the calculate that does the field  Schedule Variance % that appear in the task object.

 

When I add this field in the list of tasks appear empty.

ListOfTaskt.jpg

 

In this field appear the following calculat:

((ev_bcwp - ev_bcws)/ ev_bcws)*100

 

Note: At this moment we do not assign resources to tasks.

 