Hello! We are on 14.3. All our projects are set up with "Effort" on the "% Complete calculation" method. This means that the field is dimmed on the task screen. But, when I want to change any field on this screen (the task name for instance), and when I click on the save button, I receive an error  "ERROR PRJ-07246: Task percent complete cannot be changed with current project complete calculation method." The only way to change something on a task is to temporary change the complete calculation method for the project to "manual". Is this a normal behavior or did I miss something somewhere? Thanks!