Hi All,

 

After DWH setup, we have completed jaspersoft installation by running jobs.

1. create and update jaspersoft job - successfully completed

2. time slice job - completed

3. load datawarehouse -failed (in bg-dwh log, am getting the below error)

ERROR 2016-04-28 07:23:12,286 [Thread-14] dwh.event dwh_db_check_ - An error occurred executing this job entry :

Couldn't execute SQL: BEGIN

  DWH_CFG_PRE_CONFIG_SP(

    P_DBLINK => 'PPMDBLINK',

  P_FULL_RELOAD => 'Y'

);

END;

)

4. i tried running  load access right job. it also completed sucessfully..

 

this issue is reporting in test environment. In our dev environment Jaspersoft implementation completed successfully.

 

Attached bg-dwh log also. Please anyone help me to sort out the