Gannt Virtual Images wrong when Rolling Date equals blank

Question asked by Dale_Stockman Champion on May 23, 2016

CA PPM 14.2, on-prem.

 

Start by noting the 2015 milestones showing in Schedule Gantt as 2014:

 

Rolling Date is set to blank, where hint text indicates leaving field blank will enable 'auto-fit.'

 

Work Around:  Change Rolling Date to non-blank (e.g. 'start of current year,' 'start of current quarter'...) the images display in their correct position on the Schedule Gantt:

 

 


  Dale