Actual vs. planned % complete values?

Question asked by David_Spreitzer on May 30, 2016
Latest reply on Oct 5, 2017 by David_Spreitzer

Hello,

 

I am using the duration based %complete method (entry on task level, automatic calculation on summary task and project level).

What I am looking for is a way to compare the this actual %complete value with a planned %complete value (calculated based on the current date).

Is there a way to implement that e.g. on task level: (current_date - start_date) / (finish_date - start_date) ?

...and have it automatically summed up on summary tasks and project level?

 

Regards,

David