Task Dependencies

Question asked by JLaRezza on Jun 3, 2016
Latest reply on Jun 8, 2016 by JLaRezza

When I link a dependent task to a predecessor task with a finish-start dependency, then change the predecessor task's finish date, the dependent task's dates do not change to align with the completion of the predecessor task. How do I get this functionality to work, as it would in Microsoft Project?