AnsweredAssumed Answered

Resource actual's are missing in PPA_WIP table

Question asked by Siddiq on Jun 18, 2016
Latest reply on Jul 5, 2016 by Chris_Hackett


Hello,

 

I have a resource who has posted his time sheet and then adjusted.

His time sheet while posted as follows,

     Date:       4 (Mon)     5(Tue)      6(Wed)     7(Thu)     8(Fri)     9(Sat)     10(Sat)

     Actual's     7.5           750            7.5           7.5          7.5      

 

Later he adjusted above time sheet as,

     Date:       4 (Mon)    5(Tue)     6(Wed)     7(Thu)     8(Fri)     9(Sat)     10(Sat)

     Actual's     7.5           7.5            7.5           7.5          7.5      

 

But the actual for the date '4' is present in the PPA_WIP table and the remaining dates 5,6,7,8,9,10 are missing.

In PPA_WIP the values present are as follows,

     Quantity:                        Transdate:

         7.5                                   04

      -742.5                                 05

         7.5                                   11

It might be some one had deleted the time entry from the WIP table.

 

So, if the same time sheet is adjusted once again and then posted, is there a chance that his entered actuals to be present in PPA_WIP table ?

 

Thank you beforehand for your help,

Siddiq