Task Status Changes in MSP

Question asked by Art_Vendryes on Jun 30, 2016
Latest reply on Jun 30, 2016 by Maria_Whiteside

We are using version 14.2 along with MSP 2010.  We are finding when a task is completed in MSP (marked 100% complete) and saved back to Clarity the task shows and 100% and marked complete.  When we open the project again in MSP the same task has reverted to 99% complete.  The project % complete calculation has been set to Manual.  Has anyone run into this?  If so, any suggestions as to a solution?