In Clarity I had an existing process which does forward stage movement and another process which does backward stage movement.

Their was a requirement to add 2 more stages in the forward stage and accordingly the backward stage process should also get updated.

 

The forward stage movement process works perfectly. But in the backward stage movement when the new stage is to be moved to it does trigger the process but the process does not gets completed.

For the existing stage the backward process works fine.

 

I tried with multiple attempts but same issue sustains.

 

A help on this issue is appreciated and if you need any further details please let me know.