Autoscheduling moving dates

Question asked by Art_Vendryes on Aug 18, 2016
Latest reply on Aug 29, 2016 by Art_Vendryes

We have a project with only 14 tasks plus a summary task.  Each task is resource loaded with estimates.  There are no dependencies on the tasks.  Once of the tasks has one resource that is allocated at 25%, 57 days in duration with a start date of 10/10/16 and finish date of 12/30/16. There are no actuals and ETC of 114 hours.  When we auto-schedule in the Clarity Gantt (without resource constraints) the dates are moved to start of 1/2/17 and finish of 3/21/17.  Anybody come across this before?  If so, what was the reason and resolution?