AnsweredAssumed Answered

Timeslice for table PRJ_BLB_SLICES_M_ACT

Question asked by Allison.nichols on Aug 25, 2016
Latest reply on Aug 25, 2016 by urmas

We have a query that runs (in part) against the table PRJ_BLB_SLICES_M_ACT.  The slice periods for that table only go back to 8-1-2015 (so one year back).  I need to change that to include all of 2015 (making it 2 years back, basically).

 

If I go to Administration->Time Slices, I can see where to change the From date and the Number of Periods - however, I can't figure out WHICH Timeslice is the one that affects that table!  Anyone know?

Outcomes