  • 1.  Task Percent Complete

    Posted Sep 09, 2016 03:44 PM

    I am trying to troubleshoot an issue and seeing something in the plan that I want to verify.  I remember in earlier versions of CA PPM, when a task had actuals applied the % Complete automatically changed to 1% and the PM had the opportunity to change that percentage.  I was just wondering if that is still the case in 14.2.  The project is set to % Complete Calculation of Manual.



  • 2.  Re: Task Percent Complete
    Best Answer

    Posted Sep 09, 2016 05:29 PM

    I believe when it is set to manual the user would need to manually update this field unless you are using %expended which is calculated. You can choose to make the % Complete field calculated based off of effort or duration. There is job you would need to run in order for the calculation to display.

     

    Thanks

    Tammi



  • 3.  Re: Task Percent Complete

     
    Posted Sep 14, 2016 05:14 PM

    Hi Art_Vendryes - Did Tammi's response help answer your question? If so please mark as Correct Answer. Thanks!



  • 4.  Re: Task Percent Complete

    Posted Sep 16, 2016 07:26 AM

    Hi Chris, we will need to go through some testing to verify, but gives a lead as to what may be happening