CA PPM 14.2 EVM 0/100 Earned Value at Task Level

Question asked by JohnGMoore on Sep 27, 2016
Latest reply on Sep 27, 2016 by Antonio_Arenas

We are using Clarity PPM 14.2 and trying to use the EVM processing for that application.  We have setup some projects in our development environment with the 0/100 EVM calculation method.  However, when we complete tasks in the project and run the Update Earned Value and Cost Totals job, it does not calculate an earned value for that portion of the project.  The CA documentation does not specifically indicate that earned value is calculated at the task level.  We would like to use the 0/100 calculation method at the task level.  Does anyone know the appropriate settings in CA to make that happen?