Clarity

  • 1.  CA PPM Timesheets

    Posted Oct 07, 2016 03:12 AM

    Hi All

     

    We have just installed and trying to run our PPM. When trying to test timesheet entry, we cannot get the list of the open timesheets. Can anybody assist us?

     

    Best regards.



  • 2.  Re: CA PPM Timesheets

    Posted Oct 07, 2016 03:26 AM

    Hi Yaman_Yazgan,

    Can you please check your Time Reporting Periods and their status.

    Here are the steps to check status?

    Go to Administration-->Click on Time Reporting Periods (Under Project Management). See below screen shot for your reference.



  • 3.  Re: CA PPM Timesheets

    Posted Oct 07, 2016 03:28 AM

    I've checked and I can see 3 timesheets and with open status... 



  • 4.  Re: CA PPM Timesheets
    Best Answer

    Posted Oct 07, 2016 03:35 AM

    I have found it. Track mode was not selected as PPM. 

     