AnsweredAssumed Answered

Release & Iteration Burndown Graph / App - at task level

Question asked by 310f69876eba0edd3b58a9086c23c800 on Aug 22, 2016
In RallyDev, the Release & Iteration Burndown app only reports burndown when an item is Accepted. In other words, if the item is not accepted, any tasks which have been completed under the work item are not burnt down in the Release & Iteration Burndown Graph.
Is it possible to burndown time at the Task level? Or is there an app which will do this for me?

Thanks,
Jamie

Outcomes