This probably has an obvious answer, but I am a little perplexed.  When I am creating releases in rally the End Date (i.e. release date) of a Release sometimes changes to the next day. Perhaps this has something to do with timezones?

For example, I am based in London and am currently trying to add the following releases for our product:

Release 1: Start=10th Sep 2014 -  End = 4th Nov 2014
Release 2: Start =5th Nov 2014 - End = 30 Dec 2014

When I pick those exact dates from the picker I end up with the following:
Release 1: Start=10th Sep 2014 -  End = 5th Nov 2014
Release 2: Start =5th Nov 2014 - End = 30 Dec 2014

Strangely release 2 is ok in this scenario, but release 1's end date automatically changes.

Am I doing something wrong?