Hey Kristy, after reading this help article about 40 times: Progress Charts | CA Agile Central Help I think that what most likely happened here is the To Do Hours or the Task Estimate were set at day 1 of your iteration. Then, as the iteration went on, there may have been a change in the To Do hours which lowered the blue bar at the start of the iteration. However, the ideal line is set where it was on Day 1. I think.