Clarity

  • 1.  MS project With Clarity

    Posted Nov 16, 2016 02:40 AM

    Hello,

     

    After save MS project in clarity the Task ID saved empty. should be save automatic from generated ID clarity site.

     

    The Text1 in MSP Empty, we need to fill ID from clarity site auto generated once i send the data to clarity.

     


    Best Regards,



  • 2.  Re: MS project With Clarity

    Posted Nov 16, 2016 02:55 AM

    MSP can not pick up the autonumbering from Clarity. If you truly want to use the autonumbering for tasks you must create the tasks in Clarity before they are exported to MSP.

     

    http://www.ca.com/us/services-support/ca-support/ca-support-online/knowledge-base-articles.tec1661156.html

     

    NJ



  • 3.  Re: MS project With Clarity