Is it possible to associate a test case with more than one work item in Rally?

  • 1.  Is it possible to associate a test case with more than one work item in Rally?

    Posted Nov 29, 2016 05:59 PM

    I have some basic test cases that are used for basic regression testing and I also need to use them for validating a defect.  I seem to be unable to associate that test case with more than one work item.



  • 2.  Re: Is it possible to associate a test case with more than one work item in Rally?

    Broadcom Employee
    Posted Mar 07, 2017 12:17 PM

    Hello Karen,

     

    You can only associate a test case to one work item.  I have included the link that explains how to manage test cases.

     

    Manage Test Cases | CA Agile Central Help 

     

    Please let us know if you have any questions.

     

    Thank you,

     

    Christian