AnsweredAssumed Answered

ca clarity time periods xog issue

Question asked by Krishna4452769 on Nov 30, 2016
Latest reply on Nov 30, 2016 by Dave_3.0

All Techies,

need below help on ca clarity time periods XOG

 

when i XOG in the Time Periods using the below script the end dates are automatically rounded to friday by system however when I create manually from Clarity - Administration it is accepting the end dates as saturday or sunday.. Please help..

 

<TimePeriods>
        <TimePeriod start="2017-01-01T00:00:00" finish="2017-01-07T00:00:00" create="true" scale="weekly" openForTimeEntry="false" />
        <TimePeriod start="2017-01-08T00:00:00" finish="2017-01-14T00:00:00" create="true" scale="weekly" openForTimeEntry="false" />
        <TimePeriod start="2017-01-15T00:00:00" finish="2017-01-21T00:00:00" create="true" scale="weekly" openForTimeEntry="false" />

Outcomes