Is there a trick to XOGing in baseline dates for milestones/tasks

  • 1.  Is there a trick to XOGing in baseline dates for milestones/tasks

    Posted Dec 13, 2016 08:53 AM

    I've been trying to XOG in basline dates for milestones and tasks, but do not see them in eg OWB.

    The XOG creates a baseline for the project with dates, but even those dates are not displayed in OWB.

    No baseline dates for the tasks are created.

     

    Is there a trick to how to do that?



  • 2.  Re: Is there a trick to XOGing in baseline dates for milestones/tasks
    Best Answer

    Posted Dec 15, 2016 04:59 PM

    Not really.

    If there is previously no baseline the baseline to be written has to be current otherwise nothing is written.

    If there already is a baseline (current) you can write more noncurrent baselines with minimum project and task data.