  • 1.  Tasks are not copied when a project is created from a Template

    Posted Dec 16, 2016 04:00 AM

    We are trying to create a Project from a Template. But for one of the template the tasks are not copied.

    Can you let us know what might be the reason for tasks not being copied.

    Thanks in Advance

     

    Regards,

    Anusha



  • 2.  Re: Tasks are not copied when a project is created from a Template

    Posted Dec 16, 2016 04:42 AM

    This can also occur when there is a process in Clarity which is associated to that specific template project.



  • 3.  Re: Tasks are not copied when a project is created from a Template

    Posted Dec 16, 2016 05:24 AM

    Hi Sridhar,

     

    Thank you.

    Yes after putting the processes on Hold, the tasks are getting copied. 

    But is there any way so that the processes are active and the tasks are getting copied as well.

     