  • 1.  ETC Cost Zero

    Posted Feb 02, 2017 06:49 AM

    Hello,

    I am working on a JaspertSoft report and need to include the ETC hours ant ETC Cost values, I am using the DWH_INV_ASSIGN_SUMMARY_FACTS table but I have noticed that there are records where the ETC hours are not zero but the ETC Cost is zero.

    I don´t know why this is happening, the problem is that I am reporting zero cost for the ETC hours in this cases.

     

    I'd appreciate very much any clue  

     

    Thanks a lot

    Pilar



  • 2.  Re: ETC Cost Zero

    Posted Feb 06, 2017 12:04 PM

    Is there a line in the Rate Matrix for the Assignment role?



  • 3.  Re: ETC Cost Zero

    Posted Feb 06, 2017 12:18 PM

    Hello Tim,

    Yes the resources assigned to the task are linked to a rate in the rate matrix