Clarity

  • 1.  overall status  on program status page

    Posted Feb 10, 2017 02:01 PM

    Replacing a calculated overall status  with a custom manual update filed on program status  page, impact any other auto calculated logic , clarity version 14.2



  • 2.  Re: overall status  on program status page
    Best Answer

    Posted Feb 14, 2017 04:08 AM

    Hi tajb

    Did you want to know whether there will be any impact or not? If that is the case, then I would say, as long as you are just creating a custom attribute which require manual input, and hide the out of the box Calculated Attribute, so that the user cannot see it, nothing will get impacted. 

     

    Now let me know if that answers your question. 

     

    Regards,

    Abhisek Dhar



  • 3.  Re: overall status  on program status page

    Posted Feb 14, 2017 06:03 AM

    Thanks Abhisek. It did not impact any existing logic