  • 1.  Resource Capacity Calculation

    Posted Mar 06, 2017 04:34 PM
      |   view attached

    In the Capacity Planning Overview portlet in 14.3, how is Capacity calculated? Individual capacity is 8.0 hours/day for all resources and personal calendars are not used to track time off. We also use a base calendar to track company holidays. Given that, I would expect the capacity for a five-member team to always be 5.00 FTEs but I get 4.76, 4.77, 5.00, 5.48, 5.50, etc. Looking at the Resource Planning: Workloads portlet the numbers (in hours) works out the way I expect.

     

    Thank you,

    Rick Peterson



  • 2.  Re: Resource Capacity Calculation

    Posted Mar 09, 2017 04:57 AM

    FTE is calculated with respect to the Calendar marked as Standard in the system. Hence, one possible reason in your case could be, the availability or hours per day of your standard calendar is not 8. 



  • 3.  Re: Resource Capacity Calculation

    Posted Mar 12, 2017 10:00 PM

    Some more details on FTE calculations, find below the KB articles:

    TEC1112555 : How is full-time equivalent (FTE) allocation calculated?

    TEC1007349: FTE is incorrect for resources whose availability does not match the Standard Calendar

     

    Updated the non-working link

     

    Regards,

    Srikanth G