I have the following client´s request: for projects with more than one year duration, calculate the BCWP and ACWP portion for the present year, for example, for a project started on 2016 they need to know the BCWP and ACWP corresponding to  2017. 

Could you give me some advice to calculate this values?. The values displayed on CA PPM are virtual, I was looking at the PRJ_EV_HISTORY but I was not been able to perform the correct calculations.