  • 1.  I have a question on CA PPM Report

    Posted Mar 24, 2017 04:33 PM

    Hi, I have a question on CA PPM Report, I want to generate the Unstaffed( Unallocated) Tasks Reports for the Project,

    Also, I want to generate the report for over allocation /under allocation for the Project level ( not OBS level). Could you please tell me how I can create it on CA PPM 15.1 Ver.? 

     

    Thank you!



  • 2.  Re: I have a question on CA PPM Report

    Posted Mar 27, 2017 03:21 AM

    Hi,

     

    See if DWH_INV_ASSIGNMENT table fulfills your requirement of determining unstaffed tasks.

     

    DWH_RES_RESOURCE and DWH_RES_PERIOD_FACTS might be of help for determining the allocation related information.