Currently trying to use the auto scheduling feature w/ each task having a start-finish dependency. The last task has a must finish date.
When auto schedule runs, the last task is in it's proper place w/ gaps between the predecessor.
How do we create it so that the predecessor ends when the last task starts and so on?