AnsweredAssumed Answered

Resource allocation set to 0% in MSP

Question asked by Fabio Cresta Employee on Mar 31, 2017
Latest reply on Mar 31, 2017 by Kristin_Schroer

Hi All.

I'm testing PPM 15.2 and I have the following problem:

1. I create a project in PPM and assign some named resources to the team.

2. A open the project on MSP, add a task and assign a resource at a % less than 100% (say, 50%)

3. I save the project to PPM and run the Allocate from Estimation action. The Allocation % is correctly set to 50% ETC in the task is correct (say 4 hours in 1 day)

4. I reopen the project in MSP and it changes the resource allocation % to 0%

 

I checked with either default allocation % for the team member at 0% and 100%, same behaviour.

I I save back the project, the ETC and allocation % in PPM are not changed

 

Anyone got the same problem?

Thanks

 

Fabio#

Outcomes