Hi All.
I'm testing PPM 15.2 and I have the following problem:
1. I create a project in PPM and assign some named resources to the team.
2. A open the project on MSP, add a task and assign a resource at a % less than 100% (say, 50%)
3. I save the project to PPM and run the Allocate from Estimation action. The Allocation % is correctly set to 50% ETC in the task is correct (say 4 hours in 1 day)
4. I reopen the project in MSP and it changes the resource allocation % to 0%
I checked with either default allocation % for the team member at 0% and 100%, same behaviour.
I I save back the project, the ETC and allocation % in PPM are not changed
Anyone got the same problem?
Thanks
Fabio#