On CA PPM, on premise, 15.2; IE 11.0.9600.18617 (lasted update from MS).
Steps to replicate:
- Create WBS with 100 or more tasks
- Scroll to task near end of task list
- Click on task and drag it left or right in time and drop it
Expected result: See task where one dropped it, with new dates in Start, Finish fields with previous dates redlined.
Actual result: Taken to top of Gantt chart.
Workaround: The vertical slide bar is in unchanged position - one can shift it up or down a small bit and be instantly taken back to shifted task and see the pending date changes.
Question: Certainly this is a bug, but is there a browser setting or other thing that we can change on our end, to resolve this, or must we rely on CA to provide a patch?
If we must wait for patch, will submit support case.
Dale