Ok – thanks for the update. An undocumented change, apparently.
In the past, one would get an error message. Just tried this on 14.2, classic interface, and it’s working as you describe.
However, I would still recommend that users not mark their tasks 100% complete in MSP. Why?
- MSP still converts remaining work to actual work
- When updating schedule, MSP will use these hours when updating subsequent task start/finish dates, giving incorrect results
It is still better, IMO, to set remaining work to zero in MSP, then update the schedule, then save back to CA PPM. IMO, it was better to have the interface generate an error on save, rather than to strip the actual hours off. The error message enforced proper handling of the remaining work.
Dale