  • 1.  What is the "Baseline Time" on a project?

    Posted Apr 12, 2017 04:45 PM

    Does anyone know how the "Baseline Time" field is populated on a project?  It is a date field and it can be different from the project start and finish dates as well as the Baseline Start and Finish Dates.  What is driving this field?



  • 2.  Re: What is the "Baseline Time" on a project?

    Posted Apr 12, 2017 05:04 PM

    Maybe it is
    PRBASETIME The system enters the current time into this field when Baseline Set was last used for a project.



  • 3.  Re: What is the "Baseline Time" on a project?

    Posted Apr 13, 2017 05:38 AM

    I agree with you. This the time(date) when the project was last baselined.