Does anyone know how the "Baseline Time" field is populated on a project? It is a date field and it can be different from the project start and finish dates as well as the Baseline Start and Finish Dates. What is driving this field?
Maybe it is PRBASETIME The system enters the current time into this field when Baseline Set was last used for a project.
I agree with you. This the time(date) when the project was last baselined.