In CA PPM 15.1 with MS Project 2016, can I disable autoscheduling completely so MSP won't mess my tasks dates?

Question asked by afefer01 on Apr 26, 2017
Latest reply on May 11, 2017 by afefer01

Hi

I'm using CA PPM 15.1 with the new interface to MS Project 2016.

Every time I open a project in MS Project, either from Clarity or from MS project itself, all the tasks dates are getting messed up.

Is there a way I can disable autoscheduling in MSP completely? It looks like I disabled every checkbox under File->options but every time a project is opened from Clarity the settings are reverted to autoscheduling...

What can I do? Any suggestions?

Thanks

Amir