Changes to Availability hours Impacting Capacity vs Deman Reporting

Question asked by LynnKells82334058 on May 1, 2017
Latest reply on May 4, 2017 by carol-ann.lorentz

How do  organizations handle a change to the availability hours when an employee who is full-time (7.75 hours/day) changes to part-time (3.875 hours per day). When  the Availability hours are revised to reflect the change in hours the capacity vs demand report shows the capacity hours for past periods (history) as the new part time hours. This makes it look like the resource was over-allocated when in fact they were not.

 

Is there a way to change the individual resource availability hours from a specific date (April 1, 2017) going forward without changing the historical reporting/data?