  • 1.  How to check Critical Path in CA PPM

    Posted May 11, 2017 04:57 AM

    How to check Critical Path in CA PPM (preferably without using OWB/ MSP)? Can some one share screenshot/ steps to be done?

     

    Thanks

    Uruj

    Uruj



  • 2.  Re: How to check Critical Path in CA PPM
    Best Answer

    Posted May 11, 2017 07:56 AM

    I get a critical path indication in Gantt, by setting the "Critical" attribute on Task. A screenshot below.

     



  • 3.  Re: How to check Critical Path in CA PPM

    Posted May 11, 2017 09:28 AM

    My competitive offer is to create a task object based object to display the critical tasks in WBS sorting sequence for a project

    Note that it only works if you have critical path calculated eg when scheduling the project.

    My understanding is that is will only display tasks and milestones.