Does plan estimate of Test Set count towards the velocity of the team after it has been accepted?

  • 1.  Does plan estimate of Test Set count towards the velocity of the team after it has been accepted?

    Posted May 31, 2017 11:45 AM

    Does plan estimate of Test Set count towards the velocity of the team after it has been accepted?



  • 2.  Re: Does plan estimate of Test Set count towards the velocity of the team after it has been accepted?

    Posted Jun 29, 2017 01:30 PM

    The platform treats Test Set points the same as Defect and Story points. So, if a Test Set plan estimate is 3, then those 3 points will be calculated as part of the total velocity of the Sprint/Iteration. That calculation does not change after the Test Set is accepted, which is the same behaviour as when Defects and Stories are accepted. Does that answer your question? If not, could you provide an example of what you are trying to determine?