Clarity

  • 1.  Gantt Status Column

    Posted Jun 20, 2017 04:42 PM

    I have one Gantt Chart with porcentaje complete = 100% but the status column no change to Complete. Any body knows how can I update that status?

     

    Gantt Chart Screen Shot



  • 2.  Re: Gantt Status Column

    Broadcom Employee
    Posted Jun 21, 2017 03:06 AM

    I can see that those tasks still have ETC, so they are not effectively "Complete". Please zero the ETC and check if the tasks change to complete.

     

    Regards



  • 3.  Re: Gantt Status Column

    Posted Jun 21, 2017 03:07 AM

    The "% Complete" field is a user entered text field and does not have business rules when a value is entered into it. The "Task Status" field has business rules that affect the % Complete field. If a task status is changed to Completed the % Complete field is populated with 100.

     

    You can also refer to CA Doc for same.

    Task status not marked Completed if Percent Complete is set to 100%. Why?