I have one Gantt Chart with porcentaje complete = 100% but the status column no change to Complete. Any body knows how can I update that status?
I can see that those tasks still have ETC, so they are not effectively "Complete". Please zero the ETC and check if the tasks change to complete.
Regards
The "% Complete" field is a user entered text field and does not have business rules when a value is entered into it. The "Task Status" field has business rules that affect the % Complete field. If a task status is changed to Completed the % Complete field is populated with 100.
You can also refer to CA Doc for same.
Task status not marked Completed if Percent Complete is set to 100%. Why?