AnsweredAssumed Answered

Period Granularity in Gantt Schedules

Question asked by Will_Lloyd on Jun 20, 2017
Latest reply on Jun 23, 2017 by jfechenbach

I have updated the Fiscal Time Periods in my Entity's properties to show:

  • Q1 spanning from April 1 to June 30,
  • Q2 from July 1 to Sep 30,
  • Q3 from Oct 1 to Dec 31, and
  • Q4 from Jan 1 to Mar 31 of each active year.

I have also set the the fiscal years to Start in April and Finish in March.

I see that this has had the desired effect in the generation of Cost Plans, but Gantt Schedules - for example in the Project Dashboard Portlet and the and Project Schedule (Crystal) Report - refer to different logic, and I am trying to determine the means to update this.

For example, a Project that is finishing on June 20, 2017, once I configure the Gantt's Time Scale to be Quarters rather than Months, shows the Project End Date to be in Q2 (calendar year) 2018 rather than in Q1 Fiscal Year 2017/18.

Is there a lookup that I should be also looking to update rather, or in addition to, the Financial Organization Structure's Entities' Fiscal Time Period settings?

Outcomes