Rally Software

Expand all | Collapse all

If I use customized scheduled state for user stories, does percent done by user story count consider the custom state?

  • 1.  If I use customized scheduled state for user stories, does percent done by user story count consider the custom state?

    Posted Jun 27, 2017 04:04 PM

    I have enabled a custom schedule state field that would come after "Accepted".  It does not appear that the Percent Done by user story count takes the custom state into consideration.  



  • 2.  Re: If I use customized scheduled state for user stories, does percent done by user story count consider the custom state?

    Broadcom Employee
    Posted Jun 28, 2017 11:36 PM

    Hi Judy,

     

    Thanks for contacting CA Agile Central Customer Support. I am very sorry to hear you are encountering this issue. If your US set the custom schedule state that after "Accepted". It should also count in "% Done by story count". 

     

    I will create a support case for this issue and check with you the detail from it.