ESP Workload Automation

  • 1.  ARFSET

    Posted Jul 25, 2017 10:28 AM

    My manager was talking to CA representative and it was stated ARF should not be used for a good end of job. Is this still the case?

     

    It was also discussed that there has been an enhancement request for a delayed trigger being considered. Is there a plan being considered for this? If so do you have a date this will be available?



  • 2.  Re: ARFSET
    Best Answer

    Posted Jul 26, 2017 08:49 AM

    ARF was designed to do 'recovery'....so, yes, ARF should NOT be used for a good end of job.  If a job ends successfully in CA 7, it goes through job completion processing.  IF ARF is used for a good end of job and IF the job record is in completion processing, ARF may not execute all the RESPONSES because job completion processing removes the job record from the queue and nothing can be done if there is no job record in the queue.

     

    As far as the enhancement for delayed job trigger, there has been no dates/decisions on this enhancement.  I strongly suggest that you 'vote' on this IDEA to give it a 'boost'.