Hi All,

 

I Like to know when dose the value gets stored in the prj_blb_slices_m_ETC table.

 

i.e : for a project and a resource the start date of the project and start date of the allocation begins on August 2017 month but there is value in the particular table for Jan 2017 month. Any idea why it so happens like this?

 

Regards,

Frederic 

 