Actual costs in Program Dashboard

  • 1.  Actual costs in Program Dashboard

    Posted Sep 28, 2017 03:11 PM
      |   view attached

    I don’t know how can I see the actual costs in Program Dashboard. I tried with different field but didn't work.

     

    I attach the image



  • 2.  Re: Actual costs in Program Dashboard
    Best Answer

    Broadcom Employee
    Posted Sep 29, 2017 12:26 AM

    Try running the Update Earned Value Totals job to get the ACWP column populated.



  • 3.  Re: Actual costs in Program Dashboard

    Posted Sep 29, 2017 09:20 AM

    Eureka! It worked. Thanks