Hi,
I would say, "the total forecast COST of your Plan of Record Cost Plan" (note that the start & end date of the cost plan can be different than the project start & end date, if it's not the case for you, then you can say Project Start & End).
Forecast can hold other values than cost (e.g.revenue).
Anthony