Hi is there anyway to stop a resource from adding tasks they aren't assigned to within their time sheets? as we have users consistently doing this.
Have you tried using the Project setting 'Prevent Unassigned Timesheet Tasks'?
I hadn't thank you, I found a way to edit this attribute and it has worked.