Clarity

  • 1.  Only assigned tasks for resource timesheet

    Posted Oct 09, 2017 09:05 PM

    Hi is there anyway to stop a resource from adding tasks they aren't assigned to within their time sheets? as we have users consistently doing this.



  • 2.  Re: Only assigned tasks for resource timesheet
    Best Answer

    Posted Oct 09, 2017 09:59 PM

    Have you tried using the Project setting 'Prevent Unassigned Timesheet Tasks'?



  • 3.  Re: Only assigned tasks for resource timesheet

    Posted Oct 10, 2017 12:16 AM

    I hadn't thank you, I found a way to edit this attribute and it has worked.